When the event hits: notice first
In the first two days nothing matters more than the notice. Open the force majeure clause and check three things: how soon notice must be given, to whom and by what method, whether registered mail, email or a specified address, and whether an official certificate must be attached. Then follow that method exactly, and send a copy through the channel the other side actually reads, keeping proof of sending. If the contract requires delivery to a registered address and you only mentioned it in a chat app, a tribunal may later find that no valid notice was given.
Keep the notice short. Describe the event with date, place and facts, for example a typhoon making landfall, a grid-wide outage, the port suspending operations or a road cut off. Identify the obligation affected, such as the delivery date of a particular lot or a particular service. Say what you have done to limit the effect. Give an expected recovery date, or promise an update by a stated time. Do not admit liability, promise compensation or waive rights in the first notice, and do not exaggerate. Claiming total impossibility when partial delivery is still possible damages your credibility.
At the same time, fix the facts internally: photographs and video of the plant or warehouse, the hours of the power or water interruption, which staff could not report for work, and suspension notices from carriers or the port. These are easy to collect on the day and hard to reconstruct a week later. If people or premises are at risk, deal with safety first; see what to do when roads are blocked after a typhoon.
After the first notice, set a regular rhythm of updates, every few days, until performance resumes.
Does the event qualify? Test it against four elements
Start with the contract's definition and then the general law. Clauses are usually drafted in one of two ways: a list of named events such as typhoon, earthquake, flood, war, government action and strikes, or a general formula covering events the party could not foresee, avoid or control. With a list, ask whether your event is on it. With a formula, ask whether each qualifier is met.
Philippine law also has a general rule on fortuitous events. Broadly, the event must be independent of the party's will; it must have been unforeseeable, or unavoidable even if foreseen; it must make performance in the normal manner genuinely impossible; and the party must not have contributed to or aggravated the harm. The last two are where the other side will attack.
On impossibility: higher cost, thinner margin or a more expensive route is generally not enough. Performance must be objectively unachievable or pointless. On absence of fault: the Philippines has a typhoon season every year, so expect to be asked why stock was not built up, why the warehouse was not secured and why no backup power was arranged. If part of the loss flows from your own lack of preparation, the excuse shrinks accordingly.
Two situations need particular care. Government action, such as a temporary stoppage order, a port closure or a change in import controls, may or may not qualify, and much depends on whether it was triggered by your own non-compliance. And a failure by your upstream supplier does not automatically excuse you towards your customer unless the contract says so.
All of this turns on the wording and the facts, so have a licensed lawyer look at it early.
Evidence to keep: official, third-party and your own
Evidence comes in three tiers, and the earlier tiers carry more weight. First, official material: weather bureau bulletins and track advisories, a local government's declaration of a state of calamity or suspension of work, notices from the port authority and coast guard suspending sailings or operations, and the power utility's outage announcements. Second, third-party documents: delay notices from the shipping line or forwarder, airline cancellations, a logistics provider's suspension notice, an insurance surveyor's report. Third, your own records: site photographs and video, attendance, production and dispatch logs.
Match the official material to the facts. National news about a typhoon does not prove that your municipality and your terminal were shut on those days. Obtain announcements tied to the specific place and dates, and keep the original links with time-stamped screenshots. Some contracts require a certificate from a chamber of commerce or an authority. Whether one can be obtained and how long it takes depends on the issuing body, so ask early instead of waiting for the other side to demand it.
Evidence must also show causation, not merely that the event occurred. If the goods were already two weeks late before the typhoon, those two weeks are not excused. Set the original schedule beside actual progress and mark which days of delay the event directly caused. A simple table with one row per day is enough, and it is far more persuasive than a general statement that the storm disrupted everything.
Where the event also damaged property, the insurance claim is a parallel track with its own notice and proof rules. See warehouse fire or theft and inventory loss and when a business insurance claim is denied.
Late notice, or no force majeure clause at all
If the notice is late, send it now. A late notice is always better than none. State honestly when the event occurred and when you learned of it, explain the delay, whether communications were down, staff could not report or safety came first, and attach the evidence. Never backdate a notice and never pretend an earlier one was sent.
The effect of lateness depends on the drafting. Some contracts make timely notice a condition of relief, so that the right is lost if the period is missed. Others simply require prompt notice, and the consequence of delay is liability for the extra loss the delay caused. The difference is large, so read the clause word by word. Even under the stricter kind, if the other party in fact knew of the event, because it is in the same city, the news was everywhere or you discussed it in chat, there may be room to argue it suffered no prejudice. That is a judgment for a lawyer with the evidence in hand.
A contract with no force majeure clause still leaves some protection. The general Philippine rule on fortuitous events applies unless the law provides otherwise, the contract provides otherwise, or the nature of the obligation requires the party to assume the risk. But the general rule is narrower than a well-drafted clause. It says nothing about notice procedure, the length of any extension or when either side may terminate, all of which must be negotiated afterwards.
Remember one boundary: an obligation to pay money is generally not excused by a fortuitous event. A typhoon that prevents delivery can support relief; a typhoon that leaves you short of cash usually supports only a request for more time. If the contract is governed by a law other than Philippine law, the rules differ, so check the governing law clause first.
Mitigation and negotiation: relief is not permission to do nothing
The party invoking force majeure must still mitigate, and this is the point the other side raises most often. Be ready to show what you did: whether you tried another route, another source, temporary power or temporary premises; whether the most urgent orders were given priority; and whether work resumed as soon as conditions allowed. Record the attempts even where they failed.
The aim of negotiation is rarely the word excused. It is a concrete supplemental arrangement. Four outcomes are common: a new delivery date; delivery in parts, starting with what can be supplied now; a price adjustment or a sharing of the additional cost; and a right for either side to terminate if the event lasts beyond a stated period, with performed parts settled at cost. Put the result in a one-page supplemental agreement signed by people with authority. It is worth more than any verbal understanding.
With Philippine counterparties, act early and be candid. A phone call when the event happens, followed at once by the written notice, usually wins cooperation. Raising force majeure only after a penalty notice arrives makes the same facts sound like an excuse. If you are the party receiving a notice, do not refuse or stay silent either. Reply in writing, ask for supporting evidence and reserve your rights.
If the other side uses the event to terminate, stop supplying or stop paying, see when a paid supplier fails to deliver. Early termination and rent after a disaster follow different rules for leases; see when a landlord terminates a commercial lease. For your specific case consult a licensed lawyer; this article is not legal advice.
Drafting the clause next time, and how Yixing can help
Do not paste a template force majeure clause into a Philippine contract. Cover at least six points: a list of events that fits local reality, namely typhoon, flood, earthquake, volcanic activity, widespread power failure, port or airport closure and temporary government orders; the period, method and address for notice; the proof required; how each side's obligations are extended; how long the event must last before termination is allowed; and what happens to payment obligations and costs already incurred.
Three operational steps help as well. Before typhoon season, check backup power, drainage and warehouse protection and keep a record of the check, because that record later proves absence of fault. Build time allowance into critical orders. And confirm that property and business interruption cover matches the real exposure. Power failures are not unusual here; see coping with power outages in the Philippines.
Yixing Travel Consultancy (SEC Registration No. CS202009551, Bureau of Immigration Accredited Agency No. CA-202624381-1) provides compliance retainer services to foreign-owned companies in the Philippines: collecting official announcements and third-party confirmations, building the event timeline, preparing first drafts of bilingual notices and supplemental agreements, attending discussions with Philippine counterparties, and referring the text to licensed counsel for review where needed. We do not replace a lawyer, and whether an event excuses performance is a legal judgment on the contract and the evidence. If the event happened today, send the notice first, then bring the contract and your site records to us and we will organise the follow-up documents. For your specific case consult a licensed lawyer; this article is not legal advice.
Frequently Asked Questions
A typhoon stopped my delivery. How soon must I notify the other party?
I sent the force majeure notice late. Can I still claim relief?
My contract has no force majeure clause. What applies?
The typhoon left me short of cash. Can I withhold payment?
Does a power outage count as force majeure?
My supplier failed because the port closed. Can I invoke force majeure against my customer?
Do I need an official force majeure certificate?